PERTH, Australia — December 17, 2025 — Leads & Copy — Paladin Energy Ltd has announced the restructuring of its syndicated debt facility with lenders Nedbank Limited (acting through its Nedbank Corporate and Investment Banking division), Nedbank Namibia Limited, and Macquarie Bank. The restructure was executed on December 18, 2025, and is conditional on customary conditions.

The original debt facility was executed in January 2024, prior to the recommencement of production at the Langer Heinrich Mine (LHM) and the company’s acquisition of Fission Uranium Corp.

The restructure aims to reduce the overall debt capacity from $150 million to $110 million, leveraging Paladin’s enhanced liquidity following the successful completion of an A$300 million equity raise and A$100 million Share Purchase Plan in 2025. It also reflects Paladin’s increasing maturity as a uranium producer as it continues to ramp up production at the LHM, while providing greater undrawn debt capacity and balance sheet flexibility.

The restructured debt facility provides Paladin with $110 million, including a term loan facility of $40 million (September 30 balance: $79.8 million) that reduces costs associated with the current debt portfolio and matures on February 28, 2029. It also includes an undrawn revolving credit facility of $70 million (September 30 balance: undrawn $50 million facility) providing additional undrawn debt capacity, maturing on February 28, 2027, with an option to extend twice by a further year.

As part of the restructure, a repayment of $39.8 million will be made to reduce the term loan facility at completion.

The key terms of the restructured debt facility include:

  • Borrower: Paladin Energy Ltd and Paladin Finance Pty Ltd (a wholly owned subsidiary of Paladin Energy Ltd)
  • Lenders: Nedbank Limited, Nedbank Namibia Limited, and Macquarie Bank Limited
  • Commitment: $40M (drawn), $70M (undrawn)
  • Security: Senior Secured
  • Repayment: Quarterly capital repayment over 12 repayment periods. Voluntary repayment Borrowers may choose to repay and redraw anytime during the availability period. Repaid in full by final maturity date.
  • Maturity: 28 February 2029, 28 February 2027, with an option to extend twice by a further year, subject to a six-month notice period and Lender approval
  • Covenants: Customary covenants, representations, and events of default for a secured debt financing with financial covenants including debt service coverage ratio, net Debt/EBITDA ratio, reserve tail ratio, and minimum cash balance

Paula Raffo, Paladin Investor Relations, +61 8 9423 8100, paula.raffo@paladinenergy.com.au

Anthony Hasluck, Paladin Corporate Affairs, +61 409 448 288, anthony.hasluck@paladinenergy.com.au

Source: Paladin Energy Ltd

×

Welcome!

Biotech Reporter is the source most up-to-date real-time, direct-from-source News Tips and Story Leads.

By Subscribing you will receive Daily Biotech Update each day at 9:30 am ET (Market Open) in your inbox and you can unsubscribe any time.