VANCOUVER, British Columbia — January 12, 2026 — Leads & Copy —
K92 Mining Inc. (TSX: KNT; OTCQX: KNTNF) has announced its production results for the fourth quarter of 2025 from its Kainantu Gold Mine in Papua New Guinea.
The company reported strong quarterly production of 47,178 ounces gold equivalent or 44,129 ounces of gold, 1,940,781 pounds of copper and 47,427 ounces of silver. Quarterly sales reached 41,344 ounces of gold, 1,726,051 pounds of copper and 44,317 ounces of silver.
Annual production hit a record 174,134 ounces gold equivalent, or 176,995 ounces gold equivalent using 2025 guidance commodity prices of $2,375 per ounce of gold, $28 per ounce of silver and $4.25 per pound of copper. This comprised 164,484 ounces of gold, 5,942,203 pounds of copper and 159,309 ounces of silver, a 16% increase from 2024. The annual production was within the company’s 2025 guidance range of 160,000 to 185,000 ounces gold equivalent.
Annual sales reached a record 161,100 ounces of gold, 5,550,751 pounds of copper and 154,559 ounces of silver.
The company reported a record quarterly ore processed of 186,198 tonnes, a 93% increase from Q4 2024, with a head grade of 8.0 grams per tonne gold equivalent, or 7.4 grams per tonne gold, 0.5% copper and 10 grams per tonne silver. This included a moderate positive gold and copper grade reconciliation versus the latest independent mineral resource estimate (September 12, 2023 effective date for Kora and Judd).
Metallurgical recoveries in Q4 reached 94.3% for gold and 93.9% for copper, exceeding the updated definitive feasibility study recovery parameters for gold (92.6%) and performing in line for copper (94.2%) (January 1, 2024 effective date). The new 1.2 million tonnes-per-annum Stage 3 Expansion Process Plant has performed well, commissioning was completed in December and all material was processed exclusively through the new plant as at the end of October.
Total material mined (ore plus waste) hit a record quarterly high of 404,205 tonnes, benefiting from the commissioning of the first material pass in Q3 2025, combined with the commencement of surface trucks operating in the Twin Incline in late Q3 2025. Total mine development hit a record of 2,787 metres, a 12% increase from Q3 2025, including a new monthly development record of 1,027 metres achieved in October 2025.
Record quarterly ore mined reached 157,882 tonnes, with mining activity across 15 levels, including the 1010, 1090, 1110, 1225, 1305, 1325, 1345, 1365, 1385 and 1405 levels at Kora, the 1185, 1345, 1365, 1385 and 1405 levels at Judd.
Commissioning and performance testing of the new 1.2 million tonnes-per-annum Stage 3 Expansion Process Plant was completed in December. Daily throughput records of 3,822 tonnes and 3,794 tonnes were achieved on December 14 and 13, respectively. As at December 31, 2025, 95% of Stage 3 Expansion growth capital has either been spent or committed and remains on budget.
During Q4, significant progress was made on key pastefill infrastructure projects including the underground Pastefill Plant, Surface Tailings Filtration Plant and the Surface Storage Facility. Concrete works for the filter press structure at the Surface Tailings Filtration Plant are complete with substantial progress made on the structural steel erection, mechanical systems, and electrical switchroom installation. Paste Binder and Filter Cake Storage Facility construction is advancing well, with detailed design and bulk earthworks complete and civil and concrete works now underway. Significant progress was made on the underground Pastefill Plant during the quarter with the 1205 Silo Chamber excavation complete and progressive release of excavation areas for construction scheduled to commence this month. The overall plant design is complete and the major contracts executed. Long-lead items for the various pastefill infrastructure projects continue to arrive on site. Progressive commissioning remains on schedule to commence mid-Q1 2026, with practical completion of commissioning of the pastefill circuit scheduled for H2 2026.
Several key Stage 3 Expansion underground construction and operational excellence projects were completed or are approaching completion during the quarter, including:
Phase 2 Ventilation Upgrade: Full ventilation upgrade completed in Q4.
Phase 3 Ventilation Upgrade: The Puma Ventilation Drive remains on schedule for completion in Q1 2026 and is now within 15 metres of surface breakthrough.
Stage 4 Expansion Ventilation Upgrade: Mechanical installation of two 2 MW variable-speed drive fans was completed in late Q4, with HV electrical works and associated infrastructure now advancing. Electrification is scheduled for completion in Q1 2026.
Decline-Incline Convergence Project: Significant progress was achieved in Q4 with 257 metres of advance completed, leaving less than 50 metres of development remaining.
A new Sandvik 517i loader has recently commenced operation, an additional Sandvik 517i loader is scheduled to be operational next month, and two more loaders are scheduled to arrive on site in Q2 2026. The truck fleet is significantly expanding, with five 30 tonne surface haul trucks having arrived on site in Q3 2025, plus six new 60 tonne surface trucks scheduled to arrive in H1 2026, and a further two new 60 tonne surface trucks scheduled to arrive in Q4 2026.
Phase 1 Power Station Expansion to 10.7 MW prime power output of generation capacity was installed and commissioned in Q4. Phase 2 Power Station Expansion has progressed significantly, with civil works for the planned expansion to 15.3 MW prime power output to deliver Stage 4 Expansion power requirements, now complete.
Two new mining fronts have been substantially developed, including five sublevels on the Twin Incline mining front and four sublevels on the Lower Kora mining front.
K92 Chief Executive Officer and Director John Lewins said the company is pleased with the performance of the Kainantu Gold Mine in the fourth quarter.
Lewins said the company delivered record annual production at the upper half of guidance, and finished the year strongly, with multiple operational records achieved in the fourth quarter.