Cerro de Pasco Resources (TSXV:CDPR) Provides Quiulacocha Tailings Project Update

MONTREAL, QC — January 9, 2026 — Leads & Copy — Cerro de Pasco Resources Inc. (TSXV:CDPR) (OTCQB:GPPRF) (FRA:N8HP) has provided an operational review and corporate update, highlighting the completed key workstreams consolidated at the Quiulacocha Tailings Project, as the Company transitions toward the next stage of project execution.

This update builds on the technical and permitting progress outlined in the Company’s December 10, 2025, news release and reflects the completion and integration of several core Phase 1 programs.

Throughout 2025, the Company completed and consolidated the principal technical, environmental and regulatory workstreams required to materially advance the readiness of the Quiulacocha Project. This work has reduced execution risk within the El Metalurgista concession, strengthened the permitting foundation, and established a well-defined pathway for advancing a comprehensive tailings reprocessing and environmental remediation solution.

The Company completed integrated Phase 1 technical programs encompassing mineralogy, metallurgy, rheology, geotechnical and hydrogeological studies, subsidence assessment, and validation of drill spacing and resource modelling methodologies. Multi laboratory metallurgical characterization programs were completed and advanced, providing a defined technical basis for scale up testing, flowsheet optimization and downstream engineering trade off evaluations.

During 2025, the Company completed preliminary logistics and transportation studies evaluating concentrate handling, storage, and regional transport alternatives, including road, rail and pipeline-based options. This work has informed downstream engineering trade off studies and continues to be refined as part of the overall project execution planning framework.

Environmental-geochemical baseline programs were completed across both wet and dry seasons, with sampling conducted at more than sixty locations. Preliminary geotechnical and hydrogeological studies were finalized, enabling stability modelling, risk assessment and the design of the Phase 2 drilling program.

During 2025, the Company closed the Declaración de Impacto Ambiental related to the Phase 1 drilling program and submitted a Declaración de Impacto Ambiental for Phase 2 drilling activities to be conducted within the existing easement area of the El Metalurgista concession. In parallel, a surface use agreement was executed with the Community of Quiulacocha, securing continuity of access for ongoing and future technical activities.

The Company also completed and consolidated the technical, regulatory and stakeholder groundwork required to support the Tailings Reprocessing Application. This work brings the project to a late stage of readiness, supporting near term advancement toward a comprehensive tailings reprocessing and environmental remediation solution encompassing the broader Quiulacocha tailings footprint and representing a decisive step toward formalizing the Company’s position with respect to the historic tailings surrounding the El Metalurgista concession.

From December 16 to 19, 2025, CDPR successfully completed Phase 1 bulk sampling at the Quiulacocha tailings facility. Shallow excavation was carried out to obtain fresh and representative tailings material. Approximately 12.3 tonnes of raw bulk material were collected, packaged and transported to Lima under frozen conditions. The material will be submitted for laboratory chemical analysis and metallurgical testing to support ongoing technical evaluation, flowsheet development and future scale up studies.

The bulk sampling program represents an important step in validating metallurgical performance under representative conditions and supporting subsequent phases of technical development.

The Company has granted an aggregate of 10,600,000 stock options to directors, officers, employees and consultants in accordance with its Stock Option Plan. The options are exercisable at a price of CAD 0.68 per common share for periods of two or five years from December 16, 2025.

Options granted to consultants vest over a twelve-month. The option grants are intended to align long-term incentives with shareholder interests as the Company advances into the next stage of project development.

On November 17, 2025, the Company entered into a consultancy agreement with 1473632 BC Ltd., an independent arm’s length Vancouver based consulting firm, for the provision of strategic advisory and business development services. The consultant is entitled to fees of CAD 25,000 per quarter for an initial term of one year, representing total consideration of CAD 100,000. Following the expiry of the initial term, the agreement may be continued on a month-to-month basis subject to mutual written agreement by both parties.

Mr. Alfonso Palacio Castilla, MIMMM/Chartered Engineer (CEng) and Senior Project Manager for CDPR, has reviewed and approved the scientific and technical information contained in this news release. Mr. Palacio is a Qualified Person for the purposes of reporting in compliance with NI 43-101.

Cerro de Pasco Resources Inc. is focused on the development of its one hundred percent owned El Metalurgista mining concession in central Peru, which hosts silver rich tailings and stockpiles accumulated over more than a century of mining. The Company’s strategy is to reprocess and remediate historic mining waste, unlocking value while advancing environmental remediation and sustainable development.

Further Information Contacts:

Guy Goulet, CEO

Telephone: +1 579 476 7000

Mobile: +1 514 294 7000

Email: info@pascoresoures.com

Donna Yoshimatsu, Senior Strategic Advisor / Investor Relations

Mobile: +1 416-722-2456

dyoshi@pascoresources.com

Source: Cerro de Pasco Resources

×

Welcome!

Biotech Reporter is the source most up-to-date real-time, direct-from-source News Tips and Story Leads.

By Subscribing you will receive Daily Biotech Update each day at 9:30 am ET (Market Open) in your inbox and you can unsubscribe any time.