Montreal, Quebec — January 15, 2026 — Leads & Copy — Amex Exploration Inc. (TSXV: AMX) (FSE: MX0) (OTCQX: AMXEF) is advancing its planned bulk sample program and Phase 1 Feasibility Study (FS) for its direct shipping ore (DSO) development strategy.
In September 2025, Amex submitted the permit application for the bulk sample program. Subject to permitting and regulatory approvals, the Company is targeting the commencement of bulk sample activities in the first half of 2026.
Key developments include:
- Major requests for quotation (RFQs) are progressing well, with long-lead items already released.
- Major services providers have been met, and discussions are on-going (contractors, equipment and infrastructure providers, consultants, etc.).
- Advanced discussions are underway for bulk sample milling at nearby facilities in the Abitibi region.
- Detailed designs (underground portal, ramp, development, stopes) have been completed and are also intended to be used for Phase 1 of the mining operation.
Accessing the Perron deposit, through an underground bulk sample, will validate certain hypotheses put forward, obtain more technical information (geology, mining, etc.), and thus develop the Perron project in a diligent conservative manner.
Amex has awarded Evomine, a Quebec-based engineering consulting firm, the mandate to complete the detailed engineering design for the planned bulk sample as well as lead the Phase 1 Feasibility Study. This integrated approach is expected to generate meaningful synergies between the bulk sample program and the Phase 1 development scenario.
In December 2025, a 120-kilogram composite of mineralized material from the Champagne Zone was sent to a metallurgical laboratory, as part of this Feasibility Study. This testing aims to further enhance the metallurgical knowledge of the zone and check compatibility with flow sheets of local mills surrounding the Perron Project.
The Phase 1 Feasibility Study remains on track for completion and release by the end of Q1, 2026. It will incorporate current market conditions, including the recent increase in gold prices, which is expected to positively impact the economics of the project. The study is intended to serve as a cornerstone document to support project permitting and future development decisions. Based on current timelines and progress, Amex continues to target a potential project start-up in 2028.
Amex continues to advance the Perron Project strategically, positioning the Company to capitalize on favorable gold market trends and deliver value to shareholders.
Scientific and technical information presented in this news release was reviewed and approved by Stephen Coates, P. Eng., an independent “Qualified Person” as defined in National Instrument 43-101 – Standards of Disclosure for Mineral Projects (the “Qualified Person”).
Amex Exploration Inc. has made significant high-grade gold discoveries, along with copper-rich volcanogenic massive sulphide (VMS) zones, at its 100%-owned Perron Gold Project, located approximately 110 kilometres north of Rouyn-Noranda, Quebec. The Perron Project in Quebec consists of 183 contiguous claims for a surface area of 65.75 km². The project hosts both bulk-tonnage and high-grade gold mineralization styles.
When combined with the adjacent and contiguous Perron West Project and Abbotsford and Hepburn Projects (including additional claims acquired through staking) in Ontario, the consolidated land package spans a district-scale 501.08 km². This extensive property lies within highly prospective geology favourable for both high-grade gold and VMS mineralization.
The Project benefits from excellent infrastructure: it is accessible by a year-round road, located just 30 minutes from an airport, and approximately 6.5 km from the Town of Normétal. It is also in close proximity to several process plants owned by major gold producers.